Parking Lot Asphalt Project


Throughout September and October, SAMLARC will be conducting parking lot maintenance and repair projects at several parks throughout the community. These projects are necessary to protect the longevity, structure, and aesthetics of the parking lots. Work will begin on September 8th and each location will have varying closure schedules; lots may have limited access during this time. Individual parking lots will be closed for approximately one (1) day as the lots are serviced.

Schedule (barring unforeseen delays)


Phase 1: Concrete Repairs

All parks will be closed starting at 7am on the date scheduled.

· September 8-9: Altisima & Cielo Vista lots partially closed

· September 8-13: Arroyo Vista lot fully closed


Phase 2: Asphalt Demolition/Grinding/Patchback/Overlay

All parks will be closed starting at 7am on the date scheduled.

· September 21-24: Altisima (fully closed)

· September 21-25: Cielo Vista (fully closed)

· September 22-24: Arroyo Vista (fully closed)

· September 22-25: North Lakeshore (amphitheater) (fully closed)


Phase 3: Asphalt Seal Coating

All parks will be closed starting at 7am on the date scheduled. Residents will not have access to the parking lot for 24 hours. Parking lots will open at 7am the following day.

· October 19: Altisima, Central, Vista Verde

· October 20: North Lakeshore, Beach Club, Monte Vista, Cielo Vista

· October 21: Cañada Vista, Arroyo Vista


For questions regarding this project, please contact Jonathon Hill, Capital & Reserve Project Manager at 949-709-0018 or jonathon.hill@fsresidential.com

22342A Avenida Empresa, Suite 102A, Rancho Santa Margarita, CA 92688

(949) 709-0010

© 2018 Santa Margarita Landscape and Recreation Corporation